PennDOT Potter and Cameron County Maintenance work schedule for the week of August 07 – August 11, 2023
Emporium/Coudersport, PA – The Pennsylvania Department of Transportation Potter and Cameron County Maintenance announces the following work schedule for the week of August 07 – August 11, 2023, weather permitting. Motorists should travel with extra caution in these and all work areas. Motorists should be aware that due to the nature of highway maintenance and emergency work, crews could be working on any highway at any time of the day or night.
Cameron County 0240
Sign Repairs:
- State Route: Various SR throughout County
Mowing:
- State Route: Various SR throughout County
Spray Patching:
- State Route: 3001 (Whittimoore Hill Road)
- State Route: 4002 (Beechwood Road)
Potter County 0260
Box Culvert Replacement: Detour in place
- State Route: 244 (Tyler Hollow area)
Sign Repairs/Replacement:
- State Route: Various SR throughout County
Pipe Replacement:
- State Route: 1001 (Sweden Valley – Brookland)
Shoulder Repair:
- State Route: 44 (Carter Camp Area)
- State Route: 3001 (East Fork Road)
Pipe Flushing:
- )
Spray Patching
- State Route: 1011 (Hickox/Ulysses Road)
- State Route: 4008 (Branch Road)
Ditching:
- State Route: 6 (Sweden Valley to Galeton)
The following work is scheduled to be completed by contractor, weather permitting:
Patriot Tree Surgeons-
State Route: 244 (Andrew Settlement – Genesee)
Traffic control: Traffic along 244 will be utilizing flaggers during work hours.
Forest View Evergreen Tree Farms– Roadside Mowing
State Route: 449 (Gold – Genesee)
State Route: 1012 (Jackson Road
State Route: 1011 (Hickox/Ulysses Road)
State Route: 1013 (Bingham Center Road)
State Route: 49 (Gold – Ulysses)
Traffic control: Shadow Vehicle will be following the tractors as they mow along roadway.
Glenn O. Hawbaker Inc– Roadway Repair
State Route: 6 (Port Allegany to Coudersport) Contractors will continue with roadway repairs and drainage upgrades.
Traffic control: Traffic along SR 6 will be utilizing flaggers during work hours; multiple work zones may be in project area.
LTT Trucking LLC– Bridge Replacement
State Route: 449 (Brookland Road)
Traffic control: Traffic along 449 will be utilizing flaggers during work hours.
Dean Construction LLC– Bridge Replacement
State Route: 44 (Intersection of Tennessee Road)
Traffic control: Bridge will be closed, and the temporary roadway will carry traffic around the work zone.