The Pennsylvania Department of Transportation McKean County Maintenance announces the following work schedule for the week of August 28 – September 1, 2023, weather permitting. Motorists should travel with extra caution in these and all work areas. Motorists should be aware that due to the nature of highway maintenance and emergency work, crews could be working on any highway at any time of the day or night.
McKean County 0250
Sign Repairs and Upgrades:
- Various State Routes throughout the County
Mowing:
- Various State Routes throughout the County
Bridge Work:
- Various State Routes throughout the County
Shoulder Cutting:
- State Route: 646 (Ridge Road)
- State Route: 4003 (Bingham Road)
- State Route: 3009 (Roberts Road)
Ditch Cleaning:
- State Route: 546 (Oil Valley Road)
Pipe Flushing:
- State Route: 44 (Shinglehouse area)
- State Route: 1006 (McCrae Brook Road)
Patching:
- State Route: 6 (Ludlow to Kane)
- State Route: 1009 (Bell Run Road)
Side Dozing:
- State Route: 46 (Smethport to Rew)
- State Route: 59 (Mt. Alton to Ormsby)
The following work is scheduled to be completed by contractor, weather permitting:
Glenn O. Hawbaker – Bridge Repair
State Route: 6 – Port Allegany
Traffic control: Traffic along SR6 in Port Allegany Borough will be controlled with temporary traffic signals.